If you become the owner land plot, which is not connected to the mains, the first step is to take care of its electrification at home. In order to provide electricity to the site, it is necessary first of all to collect a package of documents, and then submit an application to the RES. In this article we will try to tell you how to bring light to the site and how much the connection procedure costs.

Connection order

To make it clearer to you where to start, in order to independently conduct electricity to the land, we will divide the actions into two stages: organizational arrangements(collection of documents, submission of an application, etc.) and technical (in particular, design and electrical work).

Getting permission

Organizational measures imply the submission to the energy supply organization of a package of documents, such as:

  • A copy of the passport of a citizen of the Russian Federation - the owner of the site (in case of filing an application from another person, a power of attorney is attached).
  • A copy of the document confirming the ownership of the house or country cottage area.
  • Plan-scheme of the site with the location of power receiving devices and with the designation of the nearest power transmission line support, as well as indicating the exact location of all engineering systems on the site, including the gas pipeline and water supply pipes.
  • Single line diagram electrical networks the applicant.
  • Consent to the processing of personal data (in accordance with the requirements federal law“On Personal Data” No. 152 dated July 27, 2006.

Scroll required documents and the order of their registration and submission is better to clarify in the RES.

Plot data can be presented from the public cadastral map, in which the plot can be found by the cadastral number of the plot indicated in the documents for ownership.

There is such a moment that if the pole from which electricity can be connected to you is located more than 25 meters from the border of the site, then in order to bring light to the site, you will have to, and most likely at your own expense.

If everything is in order with this and the distances are within the normal range, there will be no difficulties, and by acting on our recommendation, you will be able to conduct electricity to the site. Based on these documents, the energy supply company must issue specifications, thanks to which you can already conduct light.

According to the Government Decree Russian Federation number 861 dated 12/27/2004 (clause 12), energy supply organization does not have the right to refuse you, and if it is not possible to connect electricity on time, for technical reasons, to inform the deadlines for their implementation. This may be the lack of technological connectivity, this line is operating at the limit of its capabilities, and the connection of a new subscriber will lead to a network failure. And in order to bring light to your home, you need a partial or complete modernization of the power supply network, which can take years of waiting.

In case of a positive answer, in a month you will have a document in your hands and, with a permitted power of up to 16 kW (for country house and a residential building are different), the name of the electricity meter, the introductory knife switch, the RCD protective device and the sealed box for outdoor installation.

By the way, you can save a lot of time running around the authorities and doing what you love at this time if you apply for electrification of the house via the Internet on the website "http://portal-tp.rf". In short: go through registration, submit an application, attach copies of the documents described above, there is also the possibility of a preliminary application with a calculator, an indication of the amount of the bill for connecting to the electrical network. In other words, on this site you can find out what documents are needed in order to conduct electricity to the site, even if it is without buildings, and also how much it will cost to electrify the facility.

Technical measures

We take the technical condition and go to a specialized electrical goods store. We purchase a meter, automatic machines, a sealed box for outdoor installation of an electricity meter.

We go to our personal plot, we install a box on the outer wall of the house or a prepared support, we make switching in the box according to the diagrams in the technical specifications, or a specialist will do the wiring for a fee.

Further, the wires from the street box must be led to the switchboard in your house (the article implies the presence of a ready-to-turn on light, or a prepared shield with RCDs and automatic machines in the room). If the metering board is on a separate support, far away on the border of your personal plot, you can run a cable in the ground in a trench to an electrified house. About that, we talked in detail.

The connection of electricity from the pole to the inlet switchboard of the subscriber will be carried out by the company's specialists, who will also seal the meter and draw up an act on connecting the subscriber. The wiring and laying of electrical wiring must be carried out in accordance with current norms and rules in compliance with safety regulations.

AT without fail, you also need to install a protective ground loop, in our age of technology and electrical devices it will not be superfluous at all. About that, we talked about in the corresponding article.

Supply of electricity to the shield

How much does electrification cost

As a separate item, I would like to consider the cost of conducting electricity to a summer cottage. The fact is, you can’t exactly name the price, because. it depends on many factors, namely:

  1. Distance from home to power source. In the city, the distance should not exceed 300 meters, in the countryside - 500 meters to invest in the minimum amount connections - 550 rubles.
  2. The region you are in. For example, in Moscow, connecting the power grid to your shield costs more than in the Kamchatka Territory.
  3. Attachment type - new or existing. Again, in the first case, it will be more expensive to conduct electricity.
  4. The voltage level is 0.4 kV or 6-10 kV. It is also an important indicator, although only 0.4 kV is used for a residential building, but still, if you want to connect a higher voltage to the object, consider this nuance.

These are the most significant factors on which the cost of electricity supply depends. As we said above, the exact price can be found on the website using a special online calculator. The minimum price for connecting the power grid in 2019 is 550 rubles.

You can also learn about the procedure for connecting electricity by watching this video:

What you need to electrify your own home

That's all I wanted to tell you about how to conduct electricity to the site with your own hands and how much such a procedure costs. Having familiarized yourself with the stages of work, you can proceed to the collection of documents and other actions!

Connecting a private house to the power grid in 2020 will cost a minimum amount of only 550 rubles, provided that the power of the incoming current is less than 550 kilowatts. If this figure is higher, then the price of the work will increase significantly.

Where to start

The connection of electricity to a private house begins with the fact that the applicant for connection finds out which network organization he needs to contact in order to achieve such a service.

Dear readers! The article talks about typical ways to solve legal issues, but each case is individual. If you want to know how solve exactly your problem- contact a consultant:

APPLICATIONS AND CALLS ARE ACCEPTED 24/7 and 7 days a week.

It's fast and IS FREE!

For this you need to contact municipal authority. After that, within a half-month, he will be sent the name of the company, which, according to the current procedure, is authorized to carry out installation at the address where his house is located.

Where to go

If you need to connect a private house to an electric current, you need to contact network organization with paperwork.

However, you can provide it:

In the event of a shortage of certain papers or in the event that they lack the necessary information, the employees of the structure that received them notify about this within six days after the package arrives at them. After that, you need to fill in the gaps.

At the same time, it is stipulated that it is impossible to submit applications and papers to several companies at once in order to take advantage of their competition and speed up the process.

This or that territory is served only by its own RES (district power grid), and it is with it that you need to make contact.

If the network company has all necessary documentation, she sends the draft contract in paper form in two copies to the applicant.

At the same time, they will have all the required signatures from this structure. Together with the contract, technical specifications (or specifications) will be sent.

The deadline for sending papers is half a month from the day when this structure received either the package of papers itself, or additions, if necessary.

He is given a month for this, during this period he needs to send the paper to the network company. After its receipt, the agreement is considered concluded.

If the application is received in in electronic format, the agreement is sent in the same way. Next, the applicant puts a digital signature on it.

After that, the owner of the house can begin to implement the technical conditions (TU) for connection.

If the result is positive, then the connection procedure itself is performed, as well as commissioning

Then acts are drawn up:

  • on the technical connection of the facility to the power grid;
  • on the responsibility of the parties during operation;
  • on the delimitation of ownership on the balance sheet.

Connection specifications

The technical conditions of accession (TS), which the company sends to the applicant in exchange for an application, include:

  • points of connection to the network, which, according to the norms, cannot be from the boundaries of the site at a distance exceeding 25 meters;
  • more stringent requirements of a reasonable nature to increase the throughput of the existing network;
  • criteria related to metering devices, automatic emergency elements, as well as devices for controlling the highest power.

The document also stipulates that the obligation to perform the proper range of work is assigned to the consumer inside the site, and outside - to the network organization. This document is compiled and sent exclusively free of charge.

At the same time, the provisions of the technical specifications may contain excessively strict instructions; when analyzing them, it is possible to find options for how to mitigate them.

Electrical Requirements

There are a number of requirements for system elements that must be met when a house is connected to the network:

It is recommended that the cross section of the cables Used to carry out a line with a single phase, was:
  • 0.6 centimeters in the presence of copper conductors;
  • 1.6 if they are aluminum
Two cables, zero and phase Which serve to connect to power transmission towers, should be at a distance:
  • ten centimeters if they are mounted to a wooden wall;
  • five when she's out of the brick
Cable inserted into a residential building According to the accepted scheme, it goes through a hole made inside the wall, when the wire itself is installed, it is sealed using non-combustible material, including concrete or cement, it should be located:
  • at a distance of 275 cm from the ground;
  • and one and a half meters from the window
If between the power line pole and the border of the applicant's land More than 25 centimeters, it is necessary to put supports in the gap
Connection Produced to the metering device or distribution device

Connection options

There are several ways to implement this connection:

By air In this case, the cable is pulled in this way in this environment from the the shortest distance transmission lines, this is a relatively inexpensive option, but still noticeable.

In this case, the current-carrying cable:

  • passes through the wall in the pipe and then goes to the switchgear or meter;
  • or connected from outside the house with a voltage stabilizer or also a meter, then the output wires inside the house are passed through the pipe
Hidden, the cable is pulled underground A trench is carried out along the site, into which a pipe made of asbestos-cement material is buried, inside which there is a current-carrying wire. It enters the building through a technological hole that is made in the foundation. From the power line at the entrance to the trench, the cable runs along the pole also inside the protective element

This procedure is relatively expensive, therefore, in addition, it is recommended to opt for wires made of aluminum or copper, which are characterized by increased durability.

Documents that will be needed

To connect to the power grid, you will need to provide a certain package of documents to the network organization:

Application for technological connection to power grids Such an application has several types, including for the connection of power receiving devices, the highest power of which:
  • up to 15 kilowatts, including those that were previously connected for domestic needs according to the third category of reliability, in this case only an individual submits;
  • from 15 to 150 kW for a similar category 3, in this and in all subsequent paragraphs, an application is possible both from citizens and from companies, individuals, as well as individual entrepreneurs;
  • more than 150 kW, reliability categories can be the first, second and third;
  • for a temporary connection.

This document has a set pattern that must be followed.

This request requires:

  • the name of the applicant;
  • passport data (day when issued, and number with a series);
  • place of residence;
  • placement of all devices that operate on electricity and will be connected to the network;
  • project development period;
  • the time during which all devices will be gradually connected to the network;
  • information about the maximum power they use;
  • designation of the enterprise with which the owner intends to conclude an agreement on the purchase of energy from him;
  • type of contract (purchase and sale, supply or electricity supply)
Documents for the house and plot (copies), including Certificate of ownership or an extract from Rosreestr;

The document on the basis of which this right arose

Project describing the details of electrification A sample of which can be found on the network, while in practice in many regions an individual who requests a connection of no more than 15 kW does not have to draw up such paper
Building permit If the object itself is not currently built yet

When a representative submits the papers, he will need to show a notarized power of attorney.

Video: on this topic

How much will it cost (cost)

The price of this procedure is determined by the total power of the conducted current. If it is less than 15 kilowatts, which is available only for individuals, then the cost will be only 550 rubles.

When this threshold is exceeded, it grows noticeably. At the same time, it varies by subject of the Federation, so you need to find out the tariff for your region. So, in the Moscow region, the costs will amount to about 10 thousand rubles.

The nuances of doing this procedure with your own hands

Carrying out this procedure purely with your own hands is not allowed. The main stage, directly conducting current to the house, the owner of the site can perform himself.

To do this, he will need to purchase in the store:

  • the wire;
  • corrugated pipe;
  • clamps;
  • anchor hook;
  • as well as a counter.

And those works that individuals can do with their own hands are desirable to be done only by those who have the proper skills.

This article will provide a comprehensive answer to this question in the form of instructions for action! A person who decides to build a house, a dacha, or simply use the land for some own needs will definitely face the problem of connecting to centralized electrical networks. You can connect a house, cottage or plot to centralized electrical networks both at the stage of construction of the facility, and upon its complete completion.

To solve this problem, it is necessary to determine the power consumption, the distance to the nearest power transmission line and its capabilities. If the connection of electricity to a plot without buildings, a house or a summer house is in principle impossible, then a refusal will be received without the possibility of appeal. In this case, there is only one possibility - creating local system power supply based on a generator of any kind or solar panels!

Electricity connection package

To connect electrical networks to a building or site, it is necessary to draw up and submit an application of the appropriate form to the organization that provides electricity to the area and receive from it a document authorizing connection to electrical networks. The whole process of electrification of the object is presented in the following picture.

The following set of documentation is attached to the application to the energy supply company:

  • copies of identification codes and civil passport of the owner of the object;
  • a set of copies of documents confirming the registration of property.

Important! You should be aware that when compiling and submitting an application for connection to the power grid, along with copies, you must provide the originals of all documents. If the owner has authorized a third party to carry out the connection, then a power of attorney with a notarized registration must be issued to him. It is possible to submit an application by registered mail, but this form increases the time for making a decision. In the absence of certain documents, the energy supply company is obliged to notify the applicant within 6 days!

In some power supply companies, in addition to the above documents, they may request an electrification project for the facility, with a detailed plan for the placement of electrical appliances, equipment and their specifications by power. When connecting electricity to the site, it is necessary to attach to the application a permit for construction and installation work On him. Sometimes, management companies require that the application be supplemented with original contracts and acts confirming the authenticity of the copies.

After a positive decision is made, the subdivision of the district electrical network (RES) is obliged to develop specifications for connecting electricity to a private house or plot within 1 month, which the owner must complete within 2 years. The technical specifications indicate what type of cable or wires must be used - for three phases or one. Only with strict fulfillment of all the requirements of the technical conditions, it is possible to connect the object to the electrical networks. After fulfilling all the points of the technical specifications, a connection project is being developed.

The project of electrification of a house, cottage or plot

The electrification project for a house, dacha or plot can only be developed by an enterprise that has the right to carry out such work in the form of a state license. It makes no sense to use the services of non-certified organizations - the project will not be approved by the local distribution zone and others authorized bodies. A complete set of documentation for connecting an object to electrical networks includes the following initial data:

  • topography of the site and a detailed plan for connecting to power lines;
  • cable connection scheme from the support pole to the electricity consumption meter;
  • calculation of the nominal value of the input group: automatic switch and voltage limiter;
  • ground bus project for the entire facility.

For electrical networks with a three-phase voltage, the rated power of the transformer, the capacity of the network and electrical cabinets are additionally calculated. The finished project is agreed in the RES and local authorities self-government.

Rules for connecting an object to the power grid

Approval of the project for connecting the facility to electrical networks is carried out after the presentation to the RES of the layout of electrical appliances and engineering equipment, indicating the total power consumption. This plan is necessary for the correct calculation of the required cross-section of the conductors of the wire that supplies electrical energy to the house, cottage or plot, as well as for the selection of electrical equipment. The scheme makes it possible to permit document to connect the object to the power line.

The scheme will be necessary for the selection of the cross section of the conductors of the electrical wiring cable and the parameters of devices and electrical equipment. And also its presence is mandatory to obtain permission to connect to a nearby power line. When calculating the indicators of energy consumption, it is best to make a certain margin of power, which will allow you to connect additional equipment in the future. The final stage of all these procedures is the conclusion of an agreement with the RES subdivision for connection to the main power transmission line. Technical conditions are an integral part of the contract.

After the employees of the RES carry out work on the technological connection of the facility to the power supply line, the company representative draws up an act, which is the basis for concluding an agreement for the supply of electrical energy. Connection can be carried out only by employees of the RES, in otherwise a heavy fine may be imposed. For dachas that are part of garden associations, the connection is carried out by a full-time electrician of the association.

Requirements for the electrical equipment of the connected object

Requirements for an electricity consumption meter

The characteristics of metering devices installed on connected houses, summer cottages and plots must comply with GOST 6570-96. For residential premises, the operating current of the device must be at least 30 A with an accuracy class of 2.0.

All these parameters must be considered when purchasing a meter. For cottages and private houses, it is necessary to purchase a meter with a working current of more than 50 A, and also take into account the phase of the supplied electricity.

Requirements for input distribution devices (ASU)

Input distribution device- this is an electrical panel with a set of equipment designed to control electrical circuits, protect against overloads, and so on. The ASU consists of an input cable, an on / off power supply system, grounding, RCD protection devices and other elements. The input cable is placed in a special corrugated pipe that protects it from mechanical damage. The outer wire must comply with all design characteristics in terms of power, phase and degree of protection from the effects of the external environment.

All circuit breakers, RCDs and other elements of the input distribution device are selected depending on the power consumption of electricity, with some margin. Elements of the electrical panel should not come into contact with metal structures: roof, fence, grate, and so on. Mounting power cable passing through the wall must be carried out using PVC pipes.

Options for connecting a house, cottage or plot to the power grid

There are only two such options: transmission of electricity through an overhead line and a closed underground cable. The first is the simplest and cheapest, while laying the cable is associated with serious material costs. Below are the features of the connection for both options.

1. Air line. In this case, a special cable is pulled from the power transmission tower to provide electricity to the input-distribution device. It is not difficult to make such a connection, the main thing is to observe safety precautions and regulations. Currently used for these purposes.

Attention! - This is a special insulated wire with a self-supporting capacity, which is provided by the built-in cable. Thanks to this, the cable does not sag and can withstand a large wind load. can be two-wire for a single-phase network, as well as four-wire for a three-phase network.

If the distance to the power line exceeds the normative indicators, then it is necessary to install additional supports. Very often, according to the requirements of the employees of the distribution zone, it is necessary to install the ASU and the meter on the outer wall of the building or the pole-support. This is necessary for unimpeded access of controllers to the metering device. In this case, all elements of the device must be reliably protected from moisture.

The hidden way to connect to the power grid is more aesthetic, but requires additional investment. For this option, a special cable is used, designed for laying underground.

It is more expensive than SIP and requires compliance with certain conditions during installation.

The cable for hidden connection, enclosed in a "shell" or corrugated pipe, is laid in a trench on a sand cushion, in compliance with all regulatory requirements. The wire in the prepared trench must be laid freely, without any tension. All other operations for connecting an object to the power grid using an underground cable are no different from connecting over the air.

Conclusion

After carrying out all the installation work to connect the facility to the power grid, it is necessary to invite an employee of the RES to draw up an act and seal the meter. If all work is done in accordance with regulatory documentation there will be no problems, otherwise you can get a refusal. The master will point out the shortcomings and only after they are eliminated will an act be signed and a seal placed on the counter!

Related videos

Light / Electrical connection

Raising a son, growing a tree, building a house... But building a house is not enough, it must be connected to the power grid. Without light - nowhere! But in our Russian conditions connecting to the power grid is always stressful, or rather, a small legal war.

We at EnergoVOPROS.ru try our best to help people in their struggle for energy. When you are just at the beginning of the journey, you need to understand where to start, what can be the main underwater rocks and what should be feared? To clarify the main points of the difficult process, we have collected answers to the most common questions that people ask in connection with connecting a private house to the power grid. Some of them were received from government organizations, part - given by experts EnergoVOPROS.ru

Connecting to the power grid: how much will it cost to connect a site in the village to the power grid?

I am a physical face. I bought a plot in the village. From my site to the nearest pole of the el. transmission of 70-100 meters directly, if bypassing the road, then there will be 300-400 meters, a power of 15 kW is needed. Questions:

What will be the cost of joining email? networks? poles, counter, wires, etc. at whose expense?

What documents are needed to apply?

How long is the technical connection in my case?

Answers:

In accordance with paragraph 2 of the Rules technological connection power receivers of consumers of electrical energy, facilities for the production of electrical energy, as well as facilities power grid economy belonging to grid organizations and other persons to electric networks approved by Decree of the Government of the Russian Federation of December 27, 2007 No. 861 (hereinafter referred to as the Rules), regardless of the presence or absence of the technical possibility of technological connection as of the date of the applicant’s application, the grid organization is obliged to conclude an agreement with persons maximum power power receiving devices of which is up to 15 kW inclusive (taking into account the power previously connected at a given point of connection) and the object belonging to them on the basis of ownership or on other grounds provided for by law capital construction and (or) the land plot on which the applicant's facilities are (will be) located, or the right of ownership or other legal basis for power receiving devices, as well as to carry out technological connection measures in relation to the power receiving devices of such persons.

According to paragraph 16. "b" of the Rules under the contract, the period for the implementation of technological measures cannot exceed 6 months for the applicant, the maximum connected power of which is up to 15 kW inclusive, the power supply of which is provided for by one source.

Technological connection of this applicant to the electric networks of a grid organization can be carried out with a voltage class of up to 20 kV inclusive, if the minimum distance measured in a straight line from the boundaries of the applicant's site, on which the connected power receiving devices are located, to the nearest electric network object (power line support, cable line, switchgear, substation) having the voltage class specified in the application is no more than 300 meters in cities and urban-type settlements and no more than 500 meters in rural areas.

The amount of payment for the technological connection of power receiving devices with a maximum power not exceeding 15 kW inclusive is set based on the cost of measures for technological connection EDMS-46-01-32-648 on 12.12.2011 in the amount of not more than 550 rubles (including VAT) provided that the above listed distances.

It is forbidden to impose on the applicant services and obligations that are not provided for by the Rules. No additional collection in the form of a fee for the elimination of technological restrictions, for the provision of some additional services or additional construction up to the boundaries of the applicant's land plot with a maximum connected capacity of up to 15 inclusive, in accordance with the current legislation, the applicant is not required to produce.

To conclude a contract, the applicant sends an application to the grid organization, the electric grid facilities of which are located at the shortest distance from the boundaries of the applicant's site.

In the application submitted by the applicant - individual for the purpose of technological connection of power receivers, the maximum power of which is up to 15 kW inclusive, which are used for domestic needs and other needs not related to the implementation entrepreneurial activity, and the power supply of which is provided for by one source, must be indicated:

  • Surname, name and patronymic of the applicant, series, number and date of issue of a passport or other identity document in accordance with the legislation of the Russian Federation;
  • Place of residence of the applicant;
  • Name and location of power receiving devices that need to be connected to the electric networks of the grid organization;
  • Terms of design and phased commissioning of power receiving devices (including stages and queues);
  • The maximum power of the applicant's power receiving devices.

The following documents are attached to the application:

  • A copy of the document specified in the application, proving the identity of the applicant;
  • A copy of the document confirming the right of ownership or other grounds provided by law for the capital construction facility and (or) the land plot on which the applicant’s facilities are (will be located), or the right of ownership or other grounds provided for by law for power receiving devices;
  • List and power of power receiving devices that can be connected;
  • TIN of the applicant;
  • Layout plan of power receiving devices that need to be connected to the electric networks of the grid organization (copy on a scale that allows you to determine the distance from the boundaries of the applicant's land plot to the electric grid facilities);
  • Calculation of consumer load;
  • A power of attorney or other documents confirming the authority of the applicant submitting and receiving documents, if the application is submitted to the network organization by the representative of the applicant.

For more complete information on the documents for connecting electricity to your power receiving device, you need to contact the network organization of the territorial affiliation.

Connecting to the power grid of a private house: how long do technical conditions (TU) prepare and who should fulfill them?

Hello. To connect to the power supply networks, I have to contact the power grid organization and request technical specifications. In this regard, a number of questions arise.

Question 1: how much time is given to the power grid organization to issue technical specifications and on the basis of what documents?

Question 2: after receiving the technical specifications, who should comply with the technical specifications, everything that they say (installation of poles, installation of a substation, laying wires to my site.), I pay only 550 rubles. for technological connection 380V 15kW (as I understand it, for connection on a pole)? And on the basis of what documents all the work should be done by me, the ESO, the city authorities or anyone else.

Thank you in advance for your response.

Answers:

By the time of issuance of TU: a grid organization, according to Decree 861 of the Government of the Russian Federation, is given 30 days.

According to the implementation of the specifications: if the ESO line is located at a distance not exceeding 300 meters for the city and 500 meters for the village, from the boundaries of your land plot, then the activities for the construction of electrical networks to the boundaries of your site will fall on the grid organization, according to the same 861 resolution and on All this is given to them for 6 months.

Connecting to the power grid of a private house in the city. Distance - more than 300 meters. How to be?

If the distance from the existing electrical networks of the required voltage class to the boundaries of the applicant's land plot, on which the connected power receiving devices are located, is more than 300 meters (from approximately 800 to 1500 meters), does PP-334 operate in the city? And in what terms are the SOs obliged to connect this section to the power grid?

Answers:

There may be two options. You write an application for technical specifications to the network organization and you are given technical specifications at an individual rate, i.e. the network company itself builds a line for you during the validity of the technical specifications, which is usually 2 years. Or attach a letter to the application - consent to the construction of this line at your own expense and specifications cost you 550 rubles per 15 kW. And then everything will depend on you.

Connection to power grids in the Domodedovo district of the Moscow region. Where do I need to apply, what documents are needed and how long will it take to process?

Good afternoon! We have a plot without buildings in the Domodedovo district of the Moscow Region, for the construction of a house we need a point of connection to the power grid. Where do I need to apply, what documents are needed and how long will it take to process?

Answers:

First you need to find the nearest 0.4 kV transmission line and find out on whose balance and maintenance it is, after finding out the balance, contact the network organization with an application for those. accession. After 30 days, you will be given a contract of those. connections and specifications. And then everything will depend on you how quickly you can fulfill all the points of the technical specifications and legitimize your electrical installation. From the editors of EnergoVOPROS.ru: Most likely, you need the Domodedovo Distribution Zone of the Southern Electric Grids of the Moscow United Electric Grid Company (MOESK). You can see their coordinates

Connecting a private house to the power grid: the network company missed the deadlines, refuses to connect. Where and how to complain?

On January 17, 2012, she entered into an agreement with power grids for the connection of a newly built house, received an agreement, technical conditions, fulfilled her part of the agreement (connection within the site), paid 550 rubles, the contract expired on July 19, 2012. The power grids say that no funding. Where to complain and what articles to cite as arguments? Is it necessary to require a written refusal to join the house?

Answers:

You need to prepare a written claim for violation of the terms of the contract and send it to the electric grid company. You can hand it in person to the office against the signature of the head (secretary) of the office on your copy of the claim. It is also possible by mail, but only with notification.

Please note that the claim must be addressed specifically to the legal entity, and not to its structural subdivision- RES (district of electrical networks). To do this, look at the preamble of the agreement, it must indicate the correct (full) name of this legal entity. At the end of the agreement, where the addresses and payment details of the parties are indicated, find the legal and postal addresses of the company. Better to file a claim legal address(these addresses are usually the same).

In your claim, state your demand to fulfill obligations and a promise to send your application (complaint) to the OFAS (the department of the federal tax service in your region) to hold the grid company accountable. The claim should not include any requirement that the grid company refuse to connect. In the basis of the claim, it is enough to indicate the articles Civil Code RF: 401 (grounds for liability for breach of obligation), 779 ( general provisions on the service agreement). Also add a reference to clause 16 of the Rules for Technological Connection, approved by Decree of the Government of the Russian Federation of December 27, 2004 No. 861 (it sets the terms for the execution of the contract). In your claim, indicate the period during which the network company must fulfill its obligations to you.

It is clear that if she has not fulfilled her obligations within a 6-month period, then she will not be in time for a month. However, indicate the period of one month after which you can send your complaint to the OFAS in order to hold the network company liable.